FOLLOW-UP INSPECTION
This is the first follow up inspection after the facility was closed due to a sewage back up/overflow. Observations: K21: Hot water was measured above 120F at the three compartment sink, prep sink, and mop sink. K22: No sewage back up/overflow was observed. All sinks were left running and toilets were flushed. K41: The two toilets leak from the column when flushing. Facility is okay to reopen. Ensure to dry all flooring and sanitize any remaining affected areas.
1 reported violation
- K41: Plumbing approved, installed, in good repair; proper backflow devices
The two toilets leak from the column when flushing. [CA] All plumbing and plumbing fixtures shall be installed in compliance with local plumbing ordinances, shall be maintained so as to prevent any contamination, and shall be kept clean, fully operative, and in good repair.